Week 13
What were the goals for this week?
- Obtain completed vest from tailor
- Integrate motors, wires, etc into the vest
- Meet on the 22nd
- Complete Critical Assessment Document
- Construct box either by 3D printing or by hand with wood
What was accomplished this week?
- Met on the 22nd
- Completed Critical Assessment Document
- Submitted Critical Assessment Document
- Met with Dr. Raij on the 24th
- Upgraded coding in order to code for ms times for vest
- Completed Poster
- Obtained final vest from tailor!
- Components inside vest
What are the goals for next week?
- Finalize box
- Wire everything to microcontroller
- Final testing to make sure all works
- Print Poster
- Prepare for presentation on the 5th
Are there any critical dependencies, open problems, or other things to be aware of for the next week?
- None
How many hours were spent on each goal noted above?
- Approximately 15 hrs
What were the goals for this week?
- Obtain completed vest from tailor
- Integrate motors, wires, etc into the vest
- Meet on the 22nd
- Complete Critical Assessment Document
- Construct box either by 3D printing or by hand with wood
What was accomplished this week?
- Met on the 22nd
- Completed Critical Assessment Document
- Submitted Critical Assessment Document
- Met with Dr. Raij on the 24th
- Upgraded coding in order to code for ms times for vest
- Completed Poster
- Obtained final vest from tailor!
- Components inside vest
What are the goals for next week?
- Finalize box
- Wire everything to microcontroller
- Final testing to make sure all works
- Print Poster
- Prepare for presentation on the 5th
Are there any critical dependencies, open problems, or other things to be aware of for the next week?
- None
How many hours were spent on each goal noted above?
- Approximately 15 hrs